Most purchasing errors on internal floating roofs happen at the quotation stage, not at thefactory. A single lump sum hides whether seals, inspection, access works and commissioning areincluded. This article sets out the line items a usable quotation must separate so thatcompeting offers can be put side by side.
A quotation is only comparable when every bidder prices the same enquiry. State the tankdiameter and height, whether it is new or existing, the stored product and density, the decktype, the applicable code, the jurisdiction, and the required delivery and shutdown window. Ifthe shell condition is unknown, say so and ask bidders to price a survey as a separate line.
Also state what the quotation must include: supply only, supply plus installation supervision,or full erection and commissioning. A supplier quoting supply only may appear far cheaper thanone quoting a complete retrofit, even though the scopes are entirely different.
The deck line should identify the architecture: pontoon, full-contact honeycomb or hybrid. Itshould state the deck skin material and thickness, the pontoon material and wall thickness,the joining method, and the buoyancy basis. The Ultraflote 12F specification gives a concretemodel: 3003-H14 deck skin at a stated minimum thickness, 3004-H36 flotation tubes, stainlessstructural bolting, and a defined excess buoyancy and point load. Your quote need not copythose values, but it should state equivalents.
Watch for substitutions. If a bidder offers an alternative alloy or a thinner skin to meet aprice, require the technical equivalence to be shown. A quote that names only aluminium is notspecific enough to compare with one that names a temper and thickness.
Seal scope is the most common source of later variations. The quote should separate theprimary seal, any secondary seal, the seal material, and the number and type of penetrationswith their wells. The Ultraflote specification lists standard accessories such as an accesshatch, vacuum breaker, grounding cables and anti-rotation cables; a usable quote should showwhich of these are included and which are optional.
The Indian Oil tender reviewed for this article specifies a mechanical shoe primary seal and asecondary seal, anti-static and anti-rotation devices, a pressure-vacuum relief valve and deckmanways, all to API 650 Appendix H. That level of itemisation is what a buyer should aim for,whether the project is a public tender or a private purchase.
Quotation line | Must state | Risk if missing |
Deck | Architecture, alloy temper, thickness, buoyancy basis | Hidden substitutions |
Seals | Primary and secondary type and material | Variation at installation |
Penetrations | Number, wells and gasket details | Extra cost for each well |
Inspection | Hold points and third-party scope | Unverified fabrication |
Erection | Manway access, labour, shutdown duration | Site cost surprise |
Exclusions | Explicit list of what is not included | Dispute over scope |
Require the supplier to list exclusions explicitly. A short exclusions list is often moreinformative than a long inclusion list.
Ask for the quote to be valid for a stated period. Metal prices move, and an open-endedquotation protects neither side.
Separate factory tests, third-party inspection, packing, freight, insurance and site works.Factory tests should include pontoon leak testing; the Ultraflote specification describes leaktesting seams with detecting solution at a stated air pressure before shipping. Third-partyinspection is common in public tenders, where design and quality assurance plans may need tobe vetted by an approved inspector.
Site works are where retrofit quotes diverge. Shell roundness survey, corrective work, gasfreeing, permitting, lifting equipment and the duration of the shutdown should each bevisible. Correcting shell distortion is a substantial and frequently unbudgeted item, soleaving it unpriced is not the same as it being free.
A public B2B listing for a Center Enamel aluminium internal floating roof shows an indicativeband of five thousand to twenty thousand US dollars per set, with a minimum order of one setand a stated supply capacity of sixty sets per month. That is a listing claim rather than aquotation, and it cannot tell you what a roof for a forty-metre tank in a regulated servicewill cost. It does, however, show how wide the spread can be behind a single word, because asmall deck and a large engineered roof are both sold as a set.
Use them to test reasonableness, not to set the price. A quotation far below the material costimplied by the deck area and alloy should trigger a question about scope or substitution. Aquotation far above it should be supported by identified custom work, inspection or siteconstraints.
Once quotes arrive, build a comparison sheet with the same rows for every bidder: deckspecification, seal scope, penetrations, inspection, freight, erection, commissioning, spares,documentation and exclusions. Convert each to a common delivery basis, then add the cost ofany schedule difference separately. Only then compare totals.
This is not about finding the cheapest quote. It is about finding the quote whose scopematches your requirement and whose exclusions you can accept. A slightly higher quotation withclear documentation and inspection is often cheaper once the missing items are added to thelower one.
A quotation that omits warranty and spares is incomplete. Require the warranty scope andduration to be stated, along with the response process and who performs any site work. Requirea spares list with seal material identified by specification rather than only by a supplierpart number, so that you are not locked to one source for the life of the roof.
Documentation should also be a line item: as-built drawings, material certificates, testrecords, the installation and maintenance manual, and commissioning records. These aredelivered items with a cost, and treating them as free often means they arrive late orincomplete. Put them in the quote so they are planned and inspected like any otherdeliverable.
Experienced buyers read the exclusions before the total. A quotation that excludes shellcorrective work, gas freeing, permits, third-party inspection or commissioning supervision maybe entirely honest, but the excluded items will still be needed. Add them to your own estimatebefore comparing that quote with a fuller one.
If an exclusions list is blank, ask the supplier to confirm in writing that no items areexcluded. Silence is not the same as inclusion. A short, specific exclusions list is a sign ofa well-understood scope, while a vague one usually reappears as a variation order.
The compared quotation should become the technical annex of the contract, not be replaced by ashort purchase order. Carry forward the deck specification, seal scope, inspection holdpoints, exclusions list and document deliverables. If any of them change during negotiation,record the change and re-check the commercial impact.
This is especially important when multiple rounds of price discussion have occurred. Supplierssometimes adjust scope quietly to reach a target number. Keeping the line-item quotation asthe reference makes those adjustments visible and keeps the comparison you worked hard tobuild intact.
Before awarding, compare the recommended quote once more against the original enquiry. Confirmthat the tank diameter, product density, deck type and code edition in the quote match theenquiry exactly. A surprising number of disputes begin with a supplier quoting a differentdiameter or a different product assumption than the one the buyer intended.
Then check that the person who signed the quote has authority to bind the supplier and thatthe quoted validity period has not expired. These administrative checks are unglamorous, butthey are cheap insurance at the point where the largest commitment is made.
Evidence note: no quotation or project price is quoted as a Center Enamel figure. The verifiedproject library contains no internal floating roof delivery and no floating-roof price record,so every number in this quote checklist is either an attributed market figure or a publiclisting claim, not a transaction.
Evidence note: no quotation or project price is quoted as a Center Enamel figure. The verified project library contains no internal floating roof delivery and no floating-roof price record, so every number in this quote checklist is either an attributed market figure or a public listing claim, not a transaction.
A usable quotation is one you can compare. Fix the enquiry basis, require the deck and sealspecification to be explicit, separate inspection and site works, and insist on a writtenexclusions list. Use public price bands only to test reasonableness. Then normalise the offersonto a common delivery basis and compare scope before total.
Q: What should a floating roof quotation always separate?
A: Deck specification, primary and secondary seals, penetrations, inspection, freight, erection,commissioning, spares, documentation and a written list of exclusions.
Q: Why do two quotations for the same tank differ so much?
A: Usually because of scope: seals, shell survey, corrective work, inspection and commissioningmay be included in one and excluded in the other.
Q: Are listed prices useful?
A: Only as an order-of-magnitude check. A listing band is not a quotation for your diameter,product and site conditions.
Q: Should shell roundness be in the quotation?
A: At least as a separate survey line. If the shell is out of tolerance, corrective work can adda large share of project cost and should not be assumed free.
Q: What inspection should be priced?
A: Factory pontoon leak tests as a minimum, plus any third-party inspection and design reviewrequired by your jurisdiction or client.
Q: How long should a quotation be valid?
A: Long enough for your approval cycle, but not indefinite. Ask for a stated validity periodbecause metal prices move.
Center Enamel is the trading name of Shijiazhuang Zhengzhong Technology Co., Ltd, established in 2008 and based in Shijiazhuang, Hebei Province, China. The company manufactures glass-fused-to-steel bolted tanks, fusion-bonded epoxy coated tanks, stainless steel and welded steel tanks, pressure vessels, aluminium geodesic dome roofs and floating roof systems. Aluminium dome design work is carried out against AWWA D108, API 650, ADM 2015, ASCE 7-10 and IBC 2012, and the broader product range is covered by ISO 9001, NSF/ANSI 61, CE/EN 1090, ISO 28765, WRAS and FM approvals. The company reports 30,000 installed projects and an annual output of 300,000 enamel steel plates, with technical support delivered through an international distributor network and a stated 24-hour response commitment.
If your project involves tank roofs, floating decks or the shells that carry them, send the tank diameter, shell height, product, operating temperature and site design loads. We will return a preliminary structural concept, the applicable design code basis, and a written scope that separates what is included from what the site contractor must provide.