A floating roof procurement goes wrong in a specific and repeatable way: the bidders assume different scopes, so the bids are not comparable, and the award is made on the lowest number in a set of numbers that mean different things. That is a drafting problem, and it is solved in the enquiry document rather than in the negotiation. This article covers what the enquiry has to contain, how to normalise the returned bids, and which contract clauses are worth the time to get right.
The normal way to run a procurement is to identify a shortlist first and then issue an enquiry. For floating roofs it works better in the other order: write the enquiry properly first, and let it define which suppliers are capable of responding to it. An enquiry that specifies the service, the operating envelope, the regulatory regime and the deliverables in detail will automatically exclude the suppliers who cannot respond to it, which saves the qualification exercise from becoming a second round of the same conversation.
The minimum content of a floating roof enquiry is the tank data, the product data, the operating envelope, the regulatory position, the required documentation, the installation scope and the commercial basis. The detailed rationale for each field is set out in the design information article in this series; what matters here is that they are all in one document, issued identically to every bidder, and that the bidders are asked to price against it line by line.
The single most valuable sentence in the enquiry is the instruction to list assumptions. A bidder that states its assumptions is telling you exactly where the remaining uncertainty lies, and it makes the bids comparable, because you can see which assumptions are shared and which are not. A bidder that states no assumptions has not read the enquiry closely, and that is worth knowing before the award.
Section | What it must contain | Why it belongs in the enquiry |
A. Tank data | Identification, internal diameter, shell height, shell type and material, tank construction standard, as-built arrangement drawing and penetration schedule | Everything else is derived from this and it is the only document that cannot be substituted by a supplier's own assumption |
B. Product and service data | Product name and specification, density range at operating temperature, viscosity, water content, corrosivity, temperature range, vapour pressure at working conditions | Determines the seal material, the deck material, the buoyancy calculation and which regulatory thresholds apply |
C. Operating envelope | Maximum and minimum filling levels, landing level, normal fill and draw rates and rates of change, expected turbulence, seismic condition, ambient temperature range | Determines the deck travel, the clearance, the seal movement and the structural loading case |
D. Regulatory and code basis | Jurisdiction and applicable rules, the seal hierarchy required, gauging and sampling requirements, the design standard and edition for the roof | In many jurisdictions the configuration is prescribed rather than chosen, and this must be stated in the enquiry rather than negotiated |
E. Scope of supply | Itemised deck, seal, guide rails, sleeves, drains, instruments, spares, tools, documentation, installation, supervision, commissioning and training | The single largest cause of non-comparable bids is an unitemised scope |
F. Documentation required | Design calculation package, drawings, material certificates, inspection and NDE records, buoyancy calculation with design density and contamination allowance, installation records, as-built and maintenance manuals | Determines whether the roof is acceptable to the client's own assurance process, which is a gate rather than a preference |
G. Commercial basis | Supply terms, delivery point, destination, erection sequence and site facilities, programme, payment milestones, warranty scope and spares policy, validity period | Bids priced on different commercial bases cannot be compared without adjustment |
Section E deserves particular emphasis, because it is where most enquiries fail. A scope stated as supply of an internal floating roof for the tank described is not a scope; it is a title. The scope has to be itemised so that each bidder prices each item, and so that a difference between two bids can be read directly off the table without an interpretation exercise.
Normalisation step | What it does | The question it answers |
1. Equalise the tank basis | Confirm every bid is priced against the same diameter, shell height and penetration schedule | Are the bids actually for the same tank, or for the same words? |
2. Strip the scope to a common content | List the line items each bid includes and each excludes, and value the differences against the fullest bid as the reference | How much of the gap is scope rather than value? |
3. Separate supply, delivery, erection and site cost | Pull these into distinct columns because they are frequently bundled in different ways | What is the product and what is the project? |
4. Normalise the compliance and documentation scope | List the deliverables in each bid and cost the difference in engineering time and in third-party review | Would each package pass our own assurance process? |
5. Normalise the warranty and spares | State the warranty scope, the term, the exclusions and the spares position for each bid | Who carries the risk in year five and year twenty? |
6. Convert the programme to a common basis | Express each bid against the site shutdown window and price the schedule difference separately | Is the cheapest bid also the one that fits? |
7. Compute the adjusted comparison | Apply the scope differences to the lowest headline bid and compare the adjusted figures | On equal scope, which bid is actually lower? |
Step two is where the answer usually appears. In a well-run procurement, the largest single difference between the lowest and highest bid is usually scope, and once the scope differences have been valued the gap between the adjusted figures is often much smaller than the raw spread suggested. Where the adjusted gap is small, the award should be decided on the engineering quality of the packages, the programme and the warranty structure, and the price should be the tie-breaker rather than the decision.
Six clauses do more work than the rest. The first is a capacity confirmation, in which the supplier confirms in writing that the proposed configuration does not reduce the usable capacity of the tank below the operating level the operator requires. This is a specific and real risk: the EPA reference material records that on some floating roof tanks the use of a secondary seal further limits the operating capacity, because the seal has to be kept clear of fixed roof rafters or kept in contact with the tank shell at the filling level.
The second is the design basis confirmation, requiring the supplier to state the governing load case and the product density used, and to confirm that the roof meets the regulatory requirements in the jurisdiction rather than only being described as compliant. The third is a documentation and acceptance schedule, listing the deliverables with dates and defining what constitutes acceptance, so that the handover is a process rather than a negotiation.
The fourth is a supervision and workmanship clause for installation, since the seal is fitted and adjusted on site and the as-installed seal condition is the thing that determines performance; it should require a named supervision method, written adjustment instructions and a record of the as-installed seal condition. The fifth is a defect and spares clause covering the seal, the deck coating where present, the fasteners and the supplied spares, with a stated response time and a supply route for spares through the life of the installation.
The sixth is an intellectual property and documentation clause that is easy to overlook and expensive to miss: it should establish who owns the design calculations and the as-built information, and it should require that the complete calculation and drawing package is handed over on completion without charge, because that package is an asset the operator will need throughout the life of the installation and across future tank inspections.
The competitive structure of the aluminium internal floating roof segment is documented in third-party market research. The same 2025 market study places the global market at around 525 million US dollars in 2025, forecast at around 762 million by 2032, a growth rate of roughly 5.4 percent a year, with Asia Pacific the largest region at approximately 197 million US dollars, and it names the participants, including Ultraflote, Baker Altech, Matrix Service, DirecTank, DISCUS Engineered Products, Ateco Global Industries, HMT and Centre Enamel.
For a procurement team this has two practical consequences. The first is that the shortlist is short and every bidder in it is capable, so the competition is a comparison exercise rather than a screening exercise, and the time saved on screening should be spent on the enquiry document and on the interface clarifications. The second is that the comparison will be made across genuinely different business models, from companies that fabricate in house and install with their own crews to companies that supply into a local installation contractor, which means the installation and supervision terms have to be examined closely rather than assumed to be equivalent.
It is worth noting that market research of this kind describes segments and revenue rather than engineering quality, and it should be used for orientation only. The engineering assessment still has to be done against the qualification criteria in the companion article.
Four mistakes account for most of the disappointment in this product family. The first is issuing the enquiry without the arrangement drawing, which guarantees that the bidders are pricing assumptions and that the assumptions will differ. The second is accepting the bids as returned, without normalising the scope, which produces an award based on a comparison of different things.
The third is leaving the regulatory position to be settled during evaluation. Where the seal hierarchy is prescribed, a bid priced on the wrong assumption is not a low bid, it is an unusable one, and the time lost discovering that at evaluation is expensive. The fourth is failing to state the installation scope precisely, which produces a bid that appears lower and is not, because the erection, the supervision and the temporary works have been quietly excluded.
None of these is a technical problem and none requires specialist advice to fix. They are process discipline, and the article on the design information exchange in this series addresses the content of the enquiry in detail.
Case evidence disclosure: the verified Centre Enamel project library contains no internal floating roof delivery, so no project reference is cited in this article. The market size, growth and participant information are attributed third-party market research figures, and no project parameter, price or performance figure from any installation is stated.
Comparable bids are produced by a disciplined enquiry, not by a competitive market. Write the enquiry first, with the tank data, the product data, the operating envelope, the regulatory position, an itemised scope, the documentation list and the commercial basis, and issue it identically to every bidder. Normalise the returns by scope, programme, warranty and documentation before comparing them. And put the six clauses that matter into the contract, above all the capacity confirmation and the handover of the complete calculation package. If you send us your draft enquiry or the returned quotations, we will return a normalised comparison and a recommended clause set.
Q: What should be in an internal floating roof request for proposal?
A: Seven sections: the tank data including the as-built arrangement drawing and penetration schedule; the product and service data including density range and vapour pressure; the operating envelope including filling levels, landing level and seismic condition; the regulatory and code basis including the required seal hierarchy and the design standard; the itemised scope of supply; the documentation required; and the commercial basis including delivery, erection, programme, warranty and spares. The arrangement drawing is the item most often left out and the one that most determines whether the bids are comparable.
Q: How do I compare bids that are far apart in price?
A: Normalise them before comparing. Confirm every bid is against the same tank data, then list the scope items each includes and excludes and value the differences against the fullest bid as the reference. Separate supply, delivery, erection and site cost into distinct columns. Then compare the warranty scope, the documentation scope and the programme, and finally apply the scope differences to the lowest headline bid. In a well-run procurement the largest part of the gap turns out to be scope rather than value, and the decision then belongs on engineering quality and programme fit.
Q: What contract clauses should I insist on for a floating roof?
A: Six. A capacity confirmation that the configuration does not reduce the usable capacity below the required operating level, because a secondary seal can limit tank operating capacity. A design basis confirmation stating the governing load case and the product density used. A documentation and acceptance schedule with dates and a definition of acceptance. A supervision and workmanship clause for installation, covering the as-installed seal condition. A defect and spares clause with a stated response time and a spares supply route. And an ownership clause establishing that the complete calculation and drawing package is handed over on completion.
Q: Should the seal replacement interval be contractually fixed?
A: Yes, and the contract should also carry the inspection regime rather than leaving both to good intentions. The seal is a wearing component whose life depends on the product, the shell condition and the operating regime, so the interval has to be established for the specific installation. The contractual requirement should be that the supplier defines and justifies the interval in the proposal, that the inspection regime is documented, and that the spares policy covers the seal components at the specified interval for the life of the installation.
Q: How many suppliers should I invite to quote?
A: Enough to produce a real comparison and few enough to be managed. The competitive set in aluminium internal floating roofs is short and identifiable, and most of the market research in this sector names a comparable group of specialist manufacturers, so three or four capable bidders is usually enough to generate genuine competition. The effort is better spent on the enquiry document and on the clarification workshop than on extending the bidder list.
Q: How long should the procurement take?
A: The length is governed by two things rather than by the number of bidders: the completeness of the tank data you issue, and the number of clarification rounds the documentation package generates. Bids returned against an incomplete enquiry require more clarification and therefore take longer, even though they are returned faster. Issuing a complete enquiry with the arrangement drawing and the penetration schedule is the most effective way to shorten the whole cycle, and it also shortens the technical evaluation because there is less to reconstruct.
Center Enamel is the trading name of Shijiazhuang Zhengzhong Technology Co., Ltd, established in 2008 and based in Shijiazhuang, Hebei Province, China. The company manufactures glass-fused-to-steel bolted tanks, fusion-bonded epoxy coated tanks, stainless steel and welded steel tanks, pressure vessels, aluminium geodesic dome roofs and floating roof systems. Aluminium dome design work is carried out against AWWA D108, API 650, ADM 2015, ASCE 7-10 and IBC 2012, and the broader product range is covered by ISO 9001, NSF/ANSI 61, CE/EN 1090, ISO 28765, WRAS and FM approvals. The company reports 30,000 installed projects and an annual output of 300,000 enamel steel plates, with technical support delivered through an international distributor network and a stated 24-hour response commitment.
If your project involves tank roofs, floating decks or the shells that carry them, send the tank diameter, shell height, product, operating temperature and site design loads. We will return a preliminary structural concept, the applicable design code basis, and a written scope that separates what is included from what the site contractor must provide.